The full procedures for conducting of tests for testing the plant shall be agreed between the Owner and the Contractor prior to placing of the order. Before acceptance by the Owner, the completely erected plant shall be tested by the Contractor on site under normal operating conditions. The contractor shall also ensure the correct performance of the plant under abnormal condition, where applicable, i.e. the correct working of the various emergency and safety devices.
Bidder should provide complete details of their normal procedures for the testing of the quality of erection and of the performance of the erected plant. These tests should include the following at least:
A site pressure/vacuum test on all erected pipe work to demonstrate the quality of the piping and the adequacy of joints made at Site.
All the equipments shall be test run at site to demonstrate their smooth, vibration free and trouble less operation.
Site tests shall be carried out to prove satisfactory operation of electrical interlocks for each individual equipment and for the complete system.
The control panels and instruments furnished by the Contractor shall be used for the purpose of the performance and guarantee tests. If additional instruments and other accessories are required during the test, the same shall also be furnished by the Contractor and shall remain the property of the Contractor after successful completion of the tests.

[...] 2.4.0 Site Tests [...]
Pingback by 2.2.0 AHP – Scope of Supply. « Spec Ash Handling Plant — December 3, 2009 @ 12:07 pm
[...] 2.4.0 Site Tests [...]
Pingback by 1.0 Scheme of Ash Handling System: « Spec Ash Handling Plant — December 3, 2009 @ 12:15 pm
[...] 2.4.0 Site Tests [...]
Pingback by INDEX- SPEC ASH HANDLING PLANT « Spec Ash Handling Plant — December 9, 2009 @ 7:42 am